The intelligent construction Wall Production Line is high automation, strong stability, high production efficiency, advanced technology which reduces the cost of products, improve the quality of products and production efficiency.it is the current advanced light partition board mechanized production line.

Company News Industry News

Light weight partition board installation process

Release date:2020-07-15Views:

1.Light partition board construction material preparation: according to the size of the engineering drawing, prefabricate the needed light strip boards, all kinds of boards shall be transported to the site, and the stacking site shall be flat. During stacking, the boards of different specifications shall be arranged in order to match the boards, and the vertical placement Angle shall be as vertical as possible.

2.Light weight partition board construction tools: steel tape, powder line bag, small hammer, cutting machine, nail gun, big kitchen knife, ash bucket, scraper, wire hammer, aluminum alloy by straightening rod (2m long), board saw and ash board, wooden wedge, etc.

3.Work preparation: after the construction structure is completed.Deliver the plates to the site for standby use according to the design requirements.Eject the edge line of the plate with ink line at the position where the installation line pops out on the bottom surface of the beam and plate to be installed.The installation ground will be cleaned, the protruding part of the pick chisel flat.Cement mortar is prepared, and the weight ratio of cement mortar is: fine sand: cement: = 3:1.

4. During the installation of the strip, the side of the strip shall be lifted to the position where the installation line is on the beam and the bottom surface of the strip, and the bonding surface shall be completely daubed with prepared cement mortar, and the character Angle shall be made on both sides;Installation sequence;No door hole, from the outside inside installation, there is a door hole, from the door hole to the two sides of the extension, the door hole side appropriate with the whole board, vertical board when one person in the side to push, one person in the following with a wide mouth hand pry bar pry, edge top side pry, make it squeeze tight gap, in order to squeeze the glue paste for the appropriate.When pushing, should pay attention to whether the strip has deviated from the installed edge line, and timely use vertical line and aluminum alloy .